Project Summary

A structural and cosmetic renovation of an ageing single-storey F-7 bungalow — re-plumbed, re-wired, and re-floored throughout, with the original layout reworked to open up the living and dining areas.

Spec Sheet

ScopeStructural rework, re-plumbing, re-wiring, full re-finishing
Covered Area4,200 sq ft, single storey
FlooringLarge-format porcelain tile replacing original terrazzo
KitchenFully rebuilt modular kitchen with quartz countertops
ElectricalComplete rewire to current safety standards
WindowsDouble-glazed aluminium replacing original steel frames

Build Timeline

  1. Demolition & Strip-Out

    Complete

  2. Structural Rework

    Complete

  3. Re-Plumbing & Re-Wiring

    Complete

  4. Flooring & Wall Finishes

    Complete

  5. Kitchen & Bathroom Fit-Out

    Complete

  6. Final Handover

    Complete